Questions and inquiries due by July 1st, 2026.
Electronic bids due by July 8th, 2026.
Anticipated award date in July 2026.
Fabrication and erection drawings due 45* days after award (preliminary) and 60* days after award (certified).
Initial detailed procurement, production and shipping schedule due 30* days after award (preliminary) and 40* days after award (certified).
Begin pole delivery by January 14th, 2027.
Complete pole delivery by January 15th, 2027.
Primary procurement contact — name, title, email, and phone
Additional decision-makers and their departments
Bryan Texas Utilities
The government authority in Bryan, Texas is seeking a vendor to provide services related to transmission line concrete poles. The scope includes the preparation of pole designs based on load trees or wire data, configuration drawings, and design load cases provided by Bryan Utilities or its designated consulting engineer.
Vendors will be responsible for ensuring proper hauling and handling of the concrete poles, with two-point pickup locations specified by the manufacturer. Additionally, shop drawings must indicate temporary pole storage points to prevent long-term sweep. All questions regarding this project must be submitted by July 1, 2026.