See More RFPs

Wide Street and Utility Reconstruction Service

Overview


Construction, Facilities & Maintenance
Eau Claire, Wisconsin, United StatesPosted 20 days agoDeadline: May 12th, 2026

Fit Score


Settle Intelligence

Settle helps teams find, evaluate, and respond to public RFPs. We continuously surface new opportunities, score them against your company strengths, and draft proposal responses so you can focus on the work that wins business.

SUMMARY


Comprehensive street and utility reconstruction projects on Maple, Cameron, and Mappa Streets in Eau Claire, Wisconsin, for a one-year contract.

KEY REQUIREMENTS


BUDGET

Estimate

$500,000 – $1,500,000

CONTRACT DURATION


4 months

TIMELINE


Bids must be received by May 12th, 2026 at 2:00 p.m. Local Time.

Work on Cameron Street and Mappa Street may begin on May 25th, 2026.

Work on Maple Street may begin on June 8th, 2026.

All improvements must be completed by August 28th, 2026.

QUESTION DEADLINE


May 2nd, 2026

Issuing Agency


City Of Eau Claire

Organization overview and procurement intelligence available on paid plans.

DESCRIPTION


The government authority in Eau Claire, Wisconsin seeks a vendor to provide wide street and utility reconstruction services. The scope of work includes projects on Maple Street (Third Street to First Street), requiring removal of bituminous pavement, curb and gutter, and driveway approaches, as well as sanitary sewer and services.

Cameron Street (Bellinger Street to Mapp Street) construction encompasses removal of pavements and driveway approaches, water main and services installation, unclassified excavation, subbase preparation, crushed aggregate base, concrete curb and gutter, sidewalk repair, driveway approach replacements, sawing, installation of asphaltic concrete pavement, and lawn restoration.

Mappa Street (Cameron Street to Madison Street) will involve similar work, including bituminous pavement removal, water main, sanitary sewer and services, storm sewer installation, excavation, subbase preparation, crushed aggregate base, sawing, retaining wall replacement, new asphaltic concrete pavement, and lawn restoration. The contract period is expected to last one year.

Source attribution

This Settle analysis is based on the issuing organization’s public RFP listing.