RFP Issued: March 12th, 2026
Offeror's technical questions due: April 2nd, 2026
Addendum to RFP issued, if required: April 9th, 2026
Proposals due to the City: April 22nd, 2026
Contractor oral presentations, if required: Week of May 4th, 2026
Contractor discussions/negotiations: Week of May 11th, 2026
Contract Award: May 26th, 2026
Notice to Proceed: June 9th, 2026
Kickoff Meeting: June 8th, 2026
Task Order #1 Deliverables: June 18th, 2026
Task Order #2 Deliverables: July 16th, 2026
Task Order #3 Deliverable: August 3rd, 2026
Task Order #4 Deliverable: September 10th, 2026
City of Rockville
Organization overview and procurement intelligence available on paid plans.
The contracting authority seeks a qualified vendor to provide fabrication and installation services for a comprehensive wayfinding sign package. This effort includes the redesign and construction of wayfinding signage based on a previously completed wayfinding concept plan. The redesign should preserve the existing sign designs as much as possible, with the majority of the budget dedicated to fabrication.
The project is to be implemented in several phases, beginning with Phase 1, which includes the supply and installation of 73 vehicular wayfinding signs, 8 pedestrian signs, 5 destination signs, and 5 parking signs. Vendors should be prepared to engage in a detailed, multi-phase wayfinding improvement initiative and are expected to follow the recommendations outlined in the concept plan.
A pre-bid meeting is scheduled for March 25, 2026. All potential bidders are required to submit questions by April 2, 2026.