Submit schedule of submittals for approval: 10 calendar days from NTP
Schedule of Values: 15 calendar days from NTP
Final Submittal Schedule: 30 calendar days from NTP
Submit initial CPM Schedule: 30 calendar days from NTP
Submit baseline CPM Schedule (Final) must be approved before any payment: 60 calendar days from NTP
Substantial Completion: 120 calendar days from NTP
Final Completion: 170 calendar days from NTP
Greater Cleveland Regional Transit Authority
Organization overview and procurement intelligence available on paid plans.
The government authority in Cleveland, Ohio is seeking a vendor to provide trunk line fiber optic network construction services. The scope of work includes the installation of fiber optic cable infrastructure specifically for a trunk line within the municipality.
The main cable to be provided and installed must be a 96-strand, all-dielectric self-supporting (ADSS) single mode fiber optic cable. The selected vendor will be responsible for supplying and installing all related hardware and appurtenances required to complete the fiber optic subsystem to the specified standards.
A pre-bid meeting is scheduled for March 27, 2026 to address any project-related queries and clarify requirements for interested bidders.