RFQ Issued: March 10th, 2026
Questions Due: March 27th, 2026
Proposals Due: April 6th, 2026
Interviews (if needed): Week of April 13th, 2026
Complete IFB Design and Review: January 2026
Apply for Full Funding Grant Agreement (FFGA): June 2026
FFGA Approval: September 2026
Advertise for Construction Contract Bid: October 2026
Award Construction Contract: February 2027
Issue Notice to Proceed (NTP) for Construction Contract/Begin Construction: April 2027
Construction Substantial Completion: April 2029
Commissioning of Buses Complete: May 2029
Planned Revenue Service Start Date: September 2029
Contingency Loaded Revenue Service Start Date: December 2030
Project Closeout: September 2031
Berkeley-Charleston-Dorchester Council of Governments
Organization overview and procurement intelligence available on paid plans.
The government authority in North Charleston, South Carolina is seeking qualifications from firms to provide Program Management Consultant (PMC) services for the construction phase of its rapid transit project. The desired consultant should possess expertise in Bus Rapid Transit (BRT) or comparable transit construction projects, particularly in compliance with the Federal Transit Administration (FTA) New Starts program.
The selected PMC will oversee essential functions, including cost eligibility review, Standard Cost Category (SCC) reporting, configuration and change management, safety and security certification, document control, and federal reporting. While respecting the agency’s statutory authority over construction contract administration and payment, the PMC will also act as the agency’s representative regarding sponsor oversight and federal compliance during construction, and will manage construction activities.
Key responsibilities will include schedule monitoring and integration across the various program elements and construction packages, cost monitoring and forecasting to ensure SCC alignment, as well as identification and mitigation tracking of project risks. Additionally, the PMC will coordinate construction outreach and provide strategic communication support throughout the project lifecycle.
Source attribution
This Settle analysis is based on the issuing organization’s public RFP listing.