See More RFPs

Construction Management Services at Risk

Overview


Construction, Facilities & Maintenance
Atlanta, Georgia, United States; Evans, Georgia, United States; Martinez, Georgia, United StatesPosted about 1 month agoDeadline: April 28th, 2026

Fit Score


Settle Intelligence

Settle helps teams find, evaluate, and respond to public RFPs. We continuously surface new opportunities, score them against your company strengths, and draft proposal responses so you can focus on the work that wins business.

SUMMARY


Seeking a contractor for at-risk construction management of high school additions and renovations in Evans, Georgia, including comprehensive site and building work.

KEY REQUIREMENTS


BUDGET

Verified

$82,000,000

TIMELINE


Issue RFQ/P: March 27, 2026

Mandatory Pre-Proposal Conference: April 3, 2026 @ 11:00am

Questions due: April 13, 2026 before 10:00am

Final Addenda issued: April 22, 2026

RFQ/P Responses due: April 28, 2026 @ 1:00pm

Shortlist Announced: May 8, 2026

Interviews: May 20 & 21, 2026

Board Approval: June 16, 2026

Contract Date: June 17, 2026

Schematic Design Complete: April 3, 2026

Design Development Phase Complete: July 10, 2026

Construction Document Phase 50% set: August 27, 2026

Issue for Bid Set: October 7, 2026

CMAR Issue for Bids: October 23, 2026

CMAR Receive/Open Bids: December 3, 2026

Vet Bids/Prepare GMP Amendment: January 6, 2027

Board Approval: January 12, 2027

QUESTION DEADLINE


April 13th, 2026

Issuing Agency


Columbia County School District

Organization overview and procurement intelligence available on paid plans.

DESCRIPTION


This RFP seeks a qualified vendor to provide construction management services at risk for a government authority in Evans, Georgia. The selected contractor will manage the construction of additions and renovations to a high school, overseeing all phases and aspects of the project.

Required construction services encompass demolition, site work, concrete flatwork and foundations, structural steel installation, exterior and interior masonry, roofing, installation of doors and windows, hardware, interior and exterior finishes, and other specialties. The project will require close coordination with all stakeholders to ensure timely and compliant completion.

A mandatory pre-bid meeting is scheduled for April 3, 2026, and all questions must be submitted by April 13, 2026.

Source attribution

This Settle analysis is based on the issuing organization’s public RFP listing.

Similar RFPs