Issue RFQ/P: March 27, 2026
Mandatory Pre-Proposal Conference: April 3, 2026 @ 11:00am
Questions due: April 13, 2026 before 10:00am
Final Addenda issued: April 22, 2026
RFQ/P Responses due: April 28, 2026 @ 1:00pm
Shortlist Announced: May 8, 2026
Interviews: May 20 & 21, 2026
Board Approval: June 16, 2026
Contract Date: June 17, 2026
Schematic Design Complete: April 3, 2026
Design Development Phase Complete: July 10, 2026
Construction Document Phase 50% set: August 27, 2026
Issue for Bid Set: October 7, 2026
CMAR Issue for Bids: October 23, 2026
CMAR Receive/Open Bids: December 3, 2026
Vet Bids/Prepare GMP Amendment: January 6, 2027
Board Approval: January 12, 2027
Columbia County School District
Organization overview and procurement intelligence available on paid plans.
This RFP seeks a qualified vendor to provide construction management services at risk for a government authority in Evans, Georgia. The selected contractor will manage the construction of additions and renovations to a high school, overseeing all phases and aspects of the project.
Required construction services encompass demolition, site work, concrete flatwork and foundations, structural steel installation, exterior and interior masonry, roofing, installation of doors and windows, hardware, interior and exterior finishes, and other specialties. The project will require close coordination with all stakeholders to ensure timely and compliant completion.
A mandatory pre-bid meeting is scheduled for April 3, 2026, and all questions must be submitted by April 13, 2026.